Route 65 Six-Laning Project - Springfield
Update for Week of July 17, 2017
  • Installing bridge girders for northbound Route 65 bridge over Springfield Lake
  • Bridge girder installation will limit boat traffic on Springfield Lake                                            

Work Scheduled:  

  • Installing bridge girders for new northbound Route 65 bridge over Springfield Lake
  • Building concrete barrier in Route 65 median south of Springfield Lake 

Traffic Impacts:  

  • Possible nighttime lane closings and traffic stops on northbound Route 65 at Springfield Lake during the week. Work hours: 6 p.m. to 6 a.m.
  • Kayakers and boaters on Springfield Lake blocked from floating under Route 65 due to equipment used to place bridge girders
  • Trucks entering and leaving Route 65 median in areas south of Springfield Lake
  • NORTHBOUND ROUTE 65 TRAFFIC MOVED TO SOUTHBOUND SPRINGFIELD LAKE BRIDGE.
    • Slight traffic delays occurring northbound during morning rush hour
    • Northbound speed limit reduced to 45 mph; further reduced to 40 mph in crossovers
    • Route 65 will remain open to four lanes most of the time
    • Northbound traffic will remain on southbound bridge until late summer 2017
    • Southbound Route 65 ramp from eastbound Route 60 extended across Springfield Lake bridge. Drivers encouraged to use extended ramp and merge into southbound Route 65 after crossing bridge.
  • ROAD/TRAIL CLOSINGS:
    • Timbercrest Road underneath Route 65, the Galloway Greenways trail and the James River Water trail CLOSED until fall 2017
    • Drivers urged to use alternate routes to get around the Timbercrest Road closing
    • Trail users are urged to use other Greenways trails in the area
  • Route 65 speed limit reduced to 55 mph in work zone 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Widen Route 65 to six lanes — three lanes in each direction — between Route 60 and a point south of Evans Road to continue the progress to six lane Route 65 toward Ozark
  • Widen and rehabilitate southbound Route 65 bridge over Lake Springfield to accommodate new lanes and to lengthen eastbound Route 60-to-southbound Route 65 ramp
  • Replace northbound Route 65 bridge over Lake Springfield with new, wider span to replace old bridge in constant need of repair
  • Extend northbound Route 65 ramps to Route 60
  • Prime Contractor: Emery Sapp and Sons, Columbia
  • Completion Date: November 2017
  • Total Project Cost: $21 million

 END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed