Local News Releases

Southwest District Office 417.895.7600

September 16, 2016 10:15 AM
Route 160-13 at Route 14 Intersection Widening in Nixa
Update for Week of September 19, 2016
  • Village Center Street on north side of Route 14 scheduled to reopen Sept. 19
  • McCrosky Street scheduled to CLOSED on north side of Route 14 Sept. 19 until Sept. 26 

Work Scheduled:  

  • Installing traffic signal bases and electrical wiring in new right-turn islands at intersection of Route 14 and Route 160-13
  • Pouring concrete for sidewalks along Route 14 west of Route 160-13
  • Installing storm drains and grading dirt and rock in areas mainly along Route 14 east of Route 160-13
  • Removing McCrosky Street approach on north side of Route 14 to repave it 

Traffic Impacts:  

  • STREET CLOSING: McCrosky Street on the north side of Route 14 scheduled to CLOSE between Monday, Sept. 19, and Monday, Sept. 26. Drivers will have to use other city streets to reach destinations. (McCrosky Street will not close until Village Center Street reopens.)
  • Village Center Street on the north side of Route 14 is scheduled to OPEN on Monday, Sept. 19
  • Business/street entrance pavement and sidewalks may be removed and replaced with gravel. Please use caution when traveling over gravel entrances and watch for gravel where sidewalks have been removed. 
  • Business entrances may be closed one-half at a time or one entrance may be completely closed if more than one entrance exists for a business.  Access will remain OPEN to all businesses.
  • All other work taking place AWAY from traffic during daytime hours 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Add dual left-turn lanes in each direction
  • Widen Route 14 to four lanes with a center turn lane between Fort Avenue and Estes Street
  • Convert West Street to right in/right out only at Route 14
  • Replace traffic signals at intersection of Route 160-13 and Route 14
  • Build new city street between West Street and Route 160-13 south of Route 14
  • Build new sidewalks
  • Install storm water drain pipes

Prime Contractor: Hartman and Company, Springfield

Completion Date: Fall 2016

Total Project Cost: $2.76 million.

Follow MoDOT's Southwest District:

  • Facebook: MoDOT.Southwest
  • Twitter: MoDOT_Southwest
  • Instagram: @MoDOT_Southwest
Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed