Project Facts:
- Replace Route D truss bridge over Center Creek north of Webb City
- New bridge will be 12 feet higher, 18 feet wider with no truss
- Built in 1935, bridge is experiencing severe deterioration
- Currently 5,827 vehicles per day cross the bridge
Completion: December 2019
Estimated total project cost: $3 million
Traffic Impacts:
- Route D CLOSED at the bridge during construction
- Drivers will have access to property at both ends of the bridge
- Traffic will be detoured using Route 171, Route 43 and Route 96
Project Updates
-
TRAFFIC ALERT: New Jasper County Route D/Center Creek Bridge at Oronogo OPEN to Traffic
What: Jasper County Route D bridge over Center Creek OPEN to traffic at Oronogo
When: 4:15 p.m., Friday, March 13
Details: Contractor crews finished work to build new Route D bridge over Center Creek
Project details:
- Project replaced old truss...
-
Winter Weather, Construction Delays Postpone Completion
Jasper County – Continued weather and construction issues have delayed completion of a project to replace the Route D bridge over Center Creek south of Oronogo, the Missouri Department of Transportation said.
The contractor, Hartman & Company of...
-
TRAFFIC ALERT
What: Traffic slowed or stopped on Jasper County Route D at Hawthorne Road near Webb City
When: Afternoon hours Monday, Oct. 28 and Thursday, Friday and, possibly, Saturday, Oct. 31-Nov. 2
Details:
- Contractor crews taking delivery of bridge...
-
Weather, Construction Delays Postpone Opening of
Jasper County – Wet weather and construction issues have delayed completion of a project to replace the Route D bridge over Center Creek south of Oronogo, the Missouri Department of Transportation said.
The original completion date and opening of...
-
Jasper County Route D Bridge Over Center Creek
Jasper County – The Jasper County Route D bridge over Center Creek south of Oronogo will be CLOSED for up to 160 days beginning the week of April 1, the Missouri Department of Transportation said.
Contractor crews will replace the old bridge with a...
-
Jasper County Route D/Center Creek Bridge Replacement
Webb City – Area residents are invited to learn more about a project to replace the Jasper County Route D bridge over Center Creek at a public meeting scheduled for Thursday, Feb. 8, in Webb City, the Missouri Department of Transportation said.
T...
-
MoDOT is Giving Away a Bridge
Contact Historic Preservation Specialist Julia Larson at (573) 526-3598 or MoDOT Communications at (417) 621-6584.
JASPER COUNTY – The Route D bridge over Center Creek between Webb City and Oronogo will be replaced with a new bridge in 2019. The...