Construction Activities

Route 60 passing lanes - Journagan Construction Co., was awarded the $8.6 million contract to build intermittent passing lanes from Route 37 near Monett to Route 14 near Aurora. Crews are working 24/7 as weather allows. Estimated completion date is late fall 2009.

 

Maintenance Activities

Route 39 - Nov. 6-13 - Resurfacing from Route 248 to Route 60.

Business 60 - Nov. 9-13 - Cleaning out drainage culverts.

Route 86 - Nov. 9-13 - Maintaining signs.

Various routes - Nov. 9-13 - Maintaining signs, spraying weeds and patching pavement.

 

Back to Top

 

Barton County

Construction Activities

Route 126/71 interchange - APAC-Missouri, Inc., was awarded the $4.5 million contract to build an interchange at Route 126 and Route 71. Route 126 east of Route 71 is currently closed, and Route 126 west of Route 71 will be closed Aug. 10. Estimated completion date for the project is summer 2010.

Route DD/EE and 71 interchange, and Route V/C and 71 interchanges - Brauer Excavating was awarded the $7.3 million contract to build interchanges at Routes DD/EE and V/C. Estimated completion date for both interchanges is September 2010. On July 16, Route V west of Route 71 was closed.

Route 43 resurfacing - Blevins Asphalt was awarded the $1.2 million contract to resurface from Route 160 south of Liberal to Route 54 north of Moundville. Estimated completion date is Dec. 1, 2009.

 

Maintenance Activities

Route 71 South - Nov. 9-13 - Pavement repairs from Route C to Route V.

Route 71 North - Nov. 10-19 - Pavement repairs from Route C to Route B.

Various routes - Nov. 9-13 - Mowing, drainage repairs and maintaining signs.

 

Back to Top

 

Bates County

Construction Activities

Route 71 - APAC-Missouri, Inc., was awarded the $3 million contract to resurface from Route 18 to Route A/B near Butler. Estimated completion date is late November 2009.

Route 52 East bridge replacement - Hilty Quarries was awarded the $5.9 million contract to replace the Route 52 East bridge. The detour is Route H to Route BB to Route 52. Estimated completion date is fall 2010.

 

Maintenance Activities

Various routes - Nov. 9-13 – Replacing signs and replacing culverts.

 

Back to Top

 

Cedar County

Maintenance Activities

Various routes - Nov. 9-13 – Mowing and maintaining signs.

 

Back to Top

 

Dade County

Maintenance Activities

Various routes - Nov. 9-13 - Mowing, maintaining signs and repairing drainage.

 

Back to Top

 

Jasper County

Maintenance Activities

Route D - Oct. 14-Dec. 31 - Bridge at Quaker Mill closed until further notice.

Route 71 South – Nov. 2-11 - Pavement repairs from Route H to Route M.

I-44 East – Nov. 6-10 - Resurfacing Fidelity to County Road 100.

Route 171 - Nov. 9-13 - Repairing a culvert at County Road 290.

Routes JJ and 43 - Nov. 9-13 - Patching pavement.

Various routes - Nov. 9-13 - Maintaining signs.

 

Back to Top

 

Lawrence County

Construction Activities

Route 39/I-44 interchange - APAC-Missouri of Columbia was awarded the $6.3 million contract to replace the bridge with a 5-lane bridge, realign the south outer road and add signals. Estimated completion date is Nov. 25, 2009. Traffic was moved onto the new bridge and new northbound lanes of Route 39 Oct. 16 and will be handled in this fashion until new Ramps are complete. Intermittent lane closures on I-44 are possible for duration of project.

I-44 resurfacing from Route 39 to the Greene County Line - Laying asphalt on the shoulders and replacing guardrail.

Route 39 – Resurfacing from Route 265 to Route 248.

Route 60 passing lanes - Journagan Construction Co., was awarded the $8.6 million contract to build intermittent passing lanes from Route 37 near Monett to Route 14 near Aurora. Crews should begin laying asphalt around Aug. 11. Estimated completion date is late fall 2009.

 

Maintenance Activities

Route 39 - Nov. 9 - Bridge maintenance on the Truitt Creek bridge near Route 174.

Route N - Nov. 9-13 - Laying asphalt.

Route H - Nov. 9-13 - Cleaning out ditches.

Various routes - Nov. 9-13 - Maintaining signs, spraying weeds and patching pavement.

 

Back to Top

 

McDonald County

Maintenance Activities

Route K - Nov. 9-13 - Maintaining signs.

Various routes - Nov. 9-13 - Maintaining signs and patching pavement.

 

Back to Top

 

Newton County

Maintenance Activities

Route 43 – Nov. 9-10 - Resurfacing from Business 60 to Route K.

Route 60 - Nov. 10 - Bridge maintenance near Route HH.

Various routes - Nov. 9-13 - Maintaining signs and replacing drainage pipes.

 

Back to Top

 

St. Clair County

 

Construction Activities

Route B Safe & Sound Bridge Replacement - Burk Bridge Company was awarded the $793,000 contract to replace the Monegaw Creek bridges. The road is closed until early December.

 

Maintenance Activities

Various routes - Nov. 9-13 - Mowing, patching pavement, repairing drainage and maintaining signs.

 

Back to Top

 

Vernon County

Construction Activities

Route 43 resurfacing - Blevins Asphalt was awarded the $1.2 million contract to resurface from Route 160 south of Liberal to Route 54 north of Moundville. Estimated completion date is Dec. 1, 2009.

 

Maintenance Activities

Route 71 South – Nov. 9-11 - Pavement repairs near Route BB.

Route NN - Nov. 9-13 - Installing drainage pipes.

Various routes - Nov. 9-13 - Maintaining signs.

 