Counties Impacted
Andrew
Buchanan
Route Impacted
B
DD
H
Work Type
Bridge Rehabilitation
Planning Phase

The three bridges included in this project have been identified for improvements. The Andrew County Route H Lincoln Creek Bridge was built in 1966, the Andrew County Route B Upper Neely Bridge in 1968, and the Buchanan Route DD Jenkins Creek Bridge in 1971. This project will replace the bridge decks and update guardrail to current standards.

Project Progress

In Progress
Planning & Design Phase

MoDOT contracted Benesch to design the new bridges for the Andrew County Route H Lincoln Creek Bridge, Andrew County Route B Upper Neely Bridge, and Buchanan Route DD Jenkins Creek Bridge.

milestone_icon
Complete
Public Meeting

MoDOT will offer three opportunities to receive community feedback regarding the intersection improvement project.

  1. An in-person public meeting will be held on Wednesday, May 15, 2024, from 4-6 p.m. at the Missouri Department of Transportation's Northwest District Office, 3602 N. Belt Highway, St. Joseph, MO 64506. This will be an open house style meeting and community members are welcome to drop by anytime between 4:30 - 6 p.m. to speak with project experts and provide feedback. No formal presentation will be made. (Map to NW Conference Center)
  2. View the information on this webpage and utilize the form at the bottom of the page to submit your comments and/or sign up for project-specific updates. Comments must be submitted by Wednesday, May 29, 2024. 
  3. Mail your comments to:             

                Andrew, Buchanan counties public meeting 

                Missouri Department of Transportation

                3602 North Belt Highway

                St. Joseph, MO 64506

          All comments must be postmarked by Wednesday, May 29, 2024.

We are committed to providing equal access to this event for all participants. If you need a reasonable accommodation, please contact NW District Communications at 816-901-4529 by May 10, 2024. 

milestone_icon
Contract Letting

Contractors may submit competitive bids during MoDOT's scheduled lettings. This project is scheduled to be a part of the August 2024 letting. The Missouri Highways and Transportation Commission will consider all submitted bids at its scheduled monthly meeting in September 2024. If the lowest submitted bid meets all necessary criteria, the MHTC may award contracts at that time.

milestone_icon
Construction

After the contract is awarded, MoDOT will work with the contractor to determine the construction schedule. 

milestone_icon
Image
Andrew Route H Bridge

Andrew County Route H Lincoln Creek Bridge

This image shows the Andrew County Route H Lincoln Creek Bridge. It was built in 1966.

Image
Andrew Route B Bridge

Andrew County Route B Upper Neely Bridge

This image shows the Andrew County Route B Upper Neely Bridge. It was built in 1968.

Image
Buchanan County Route DD Bridge

Buchanan County Route DD Jenkins Creek Bridge

This image shows the Buchanan County Route DD Jenkins Creek Bridge. It was built in 1971.

Webform
Sign up for email updates:
*
*
*