Counties Impacted
Jasper
Completed

Project Facts:

  • Replace Range Line Road bridge over Kansas City Southern Railroad
  • New bridge two feet higher, 15 feet wider, 27 feet shorter than current bridge
  • New bridge will include sidewalks on both sides
  • Current bridge rebuilt in 1976
  • Approximately 24,580 vehicles per day cross bridge
  • Financial incentive for early completion

Construction: Week of September 6, 2022

Completion: December 16, 2022

Estimated Total Project Cost: $6.2 million

Traffic Impacts:

  • Range Line Road bridge CLOSED for maximum of 87 calendar days
  • Access to all businesses will remain OPEN throughout the duration of the project
  • Detour: Jasper Co. Rt. FF (32nd St.), Missouri Rt. 249, Missouri Rt. 66 (7th St.), I-44