Project Summary
This project will replace the Lemon Trail (County Road 211) and Nitrogen Avenue (County Road 225) bridges over Interstate 70.
The Lemon Trail bridge is located near mile marker 81.6 on I-70 and construction is planned to begin in Dec. 2024 and completed by Aug. 1, 2025 (anticipated).
The Nitrogen Ave. bridge is located near mile marker 85.8. Construction on the project is estimated to begin in late summer 2025 once the Lemon Trail bridge is completed and open to motorists. The Nitrogen Ave. bridge is anticipated to be completed in 2026.
These bridge replacements are part of a future Improve I-70 project between Odessa and Boonville.
Project Milestones
Latest News
-
REMINDER: Improve I-70 KC Public Information Meeting on March 4 will feature project updates
JACKSON COUNTY - The Missouri Department of Transportation (MoDOT) and Clarkson-Radmacher Joint Venture teams will host a third open house public meeting for the Improve I-70 KC project between The Paseo to east of U.S. 40/31st Street. The Missouri...
-
CLOSURE scheduled for WB MO 350 at Blue Ridge Blvd., March 4-24
JACKSON COUNTY – Crews will CLOSE WB MO 350 at Blue Ridge Blvd. for heat straightening and bridge repair work under the bridge beginning Tuesday, March 4 through Monday, March 24. The recommended detour of I-470 to I-435 to WB MO 350 will be posted...
-
Periodic lane closures scheduled on I-70 in Saline Co. for bridge construction, Mar. 3 - Aug. 2025
SALINE COUNTY – The Missouri Department of Transportation will be performing periodic lane closures on Interstate 70 near mile marker 81.6 as crews rebuild the Lemon Trail bridge over the interstate. The previous bridge was removed in January 2025...
Project Files
Frequently Asked Questions:
Why is this project happening?
Both the Lemon Trail and Nitrogen Avenue bridges have been hit and are in need of replacement. The new bridges will also be built to accommodate the Improve I-70 project.
What will be the traffic implications?
I-70 will have intermittent lane closures during construction. Crossovers will be used during the demo of the bridges while still maintaining traffic flow on I-70.
Construction on the Lemon Trail bridge will begin in Dec. 2024 and will be completed in Fall 2025 (anticipated).
Construction on the Nitrogen Ave. Bridge project is anticipated to begin in Fall 2025. The Nitrogen Ave. bridge is anticipated to be completed in 2026.
What is the cost and funding?
The project is estimated to cost just under $5.5 million and is being funded through the Improve I-70 program.
Project Photos
Project Contacts

Karlee Covington
Title
Improve I-70: West Project Director
Department
Central Office
Contact Info

Ryan Kneib
Title
Improve I-70 West Deputy Project Director
Department
Kansas City District
Contact Info