October 09, 2009
Weekly Road Work for Northeast Missouri
Schedule for October 13 through October 23

HANNIBAL - The following is a list of general highway construction and maintenance scheduled for October 13 through October 23 for all counties in MoDOT's northeast district. Weather conditions may cause postponements in the work schedule. Other maintenance work may occur on other roads throughout the area. This work will include lane closures and at times delays can be expected.

Crews will be working during daylight work hours unless otherwise indicated. Various forms of traffic control will be in place to secure the safety of the motoring public as well as the safety of highway crews.

All roadwork is posted on the traveler information map on the day it begins or at least one week in advance. Those traveling and the commuting public are encouraged to check the online map at www.modot.org daily for new work zones. Drivers are also invited to rate MoDOT work zones online at modot.org. MoDOT also offers e-update messages sent directly to your email when roadwork is scheduled. Sign up online or call MoDOT's customer service center at 1-888-275-6636.

Audrain County
Construction
:
Route 15 - Project 50% complete - Contractor paving on South 54 (South Clark) between Green BLVD and Route D; work zone delays, one lane road with possible width restrictions of 10 ft.; location 24.3 miles in Audrain and Monroe Counties from one mile north of Route 22 to just north of Route 54 at Mexico.
Maintenance:
Routes U, N, T & EE - Oct. 13-16 cold mix patching, single lane traffic with flaggers.
Route 19 - Oct. 13-23 sealing cracks on roadway, single lane traffic with flaggers.
All routes - Oct. 13-23 mowing, moving operation with blocker truck.
Route W - Oct. 19-23 hot mix patching, single lane traffic with flaggers.
Various Routes - Oct. 13-16 painting H-piles under bridges, no lane closures.

Callaway County
Maintenance
:
Minor routes - Oct. 13-16 mowing, moving operation with blocker truck.
I-70 median & shoulders - Oct. 19-23 mowing, moving operation with blocker truck.

Clark County
Construction
:
Route 61/27 - Milling operations and resurfacing in progress - 85% complete - Asphalt operations at 5 disconnected sections in southbound lanes from the Iowa State line south to the Lewis County line. One-lane traffic southbound from 7 a.m. to 7 p.m. Monday thru Saturday with 14 to 16 ft. width restrictions at work zones from just north of Fox River Bridge to the 27 South/61 ramp, and from Sugar Creek Bridge to Lewis County line.
Maintenance:
Route EE - Oct. 14 closed for resurfacing from Business Route 136, just east of Kahoka, east to state maintenance ends. Crews will begin working on the east end of Route EE and will proceed west approximately 5 miles to Business Route 136. The road will be closed from 8:30 a.m. and 3:30 p.m.
Route 61 - Oct. 13-16 working on our erosion plan with the track hoe, one lane closed.
Route 27 - Oct. 13-16 hauling rock and lining ditches, one lane closed.
Route 61 - Oct. 19-23 completing erosion plan with track hoe, one lane closed.
Routes V and CC - Oct. 19-23 culvert replacement with backhoe, one lane closed.
Routes B, C, DD, 81N, EE, CC, V, portion of NN, H, F, P and Z- Oct. 13-16 mowing, moving operation with follow truck.
Routes NN, H, F, P, Z and K - Oct. 19-23 mowing, moving operation with follow truck.

Knox County
Maintenance
:
Routes E, 156W, A, J, O, Z, C, Y, EE, 11, E, P and B- Oct. 13-16 mowing, moving operation with follow truck.
Route 168 - Oct. 13-16 dirt work, no lane closure.
Routes 151, KK, BB, 156E, CC, T, U, AA, K, V, M and E - Oct. 19-23 mowing, moving operation with a follow truck.
Route 15 - Oct. 19-23 bridge work with dozer, one lane with signs.

Lewis County
Construction
:
Route E - Completed-bridge opened to traffic Oct. 8 - Wyaconda River Bridge for redecking between Route F and Route 81.
Maintenance:
Routes B, C, DD, 81N, EE, CC, V, NN, H, F, P and Z - Oct. 13--16 mowing, moving operation with follow truck.
Route 61 - Oct. 13-16 working on erosion control southbound between Canton and LaGrange, left lane closed.
Routes NN, H, F, P, Z and K - Oct. 19-23 mowing, moving operation with follow trucks.
Route 61 - Oct. 19-23 working on erosion control southbound between Canton and LaGrange, left lane closed.

Lincoln County
Construction
:
Route 61 at Route U interchange - Bridge incidental clean up; grading roadbeds in preparation for Baserock. Project 54% completed.
Maintenance:
Route J - Oct. 13-16 edgerut repair, one lane traffic with flaggers and pilot car.
Various Routes - Oct. 13-23 mowing, moving operation with blocker truck.
Routes AA, 47 & C - Oct. 19-23 hot mix patching, one lane traffic with flaggers.
Route Z bridges - Oct. 19 hot mix patching, one lane traffic with flaggers.

Marion County
Maintenance
:
Route 168 - Oct. 13-16 shoulder work, temporary lane closure.
Routes 61 and 36 - Oct. 13-16 working on erosion control under bridges, one lane with signs.
Supplementary Routes - Oct. 13-16 mowing and washing bridges, moving operation with follow truck.
Route 168 - Oct. 19 working on edge ruts, moving operation.
Route J - Oct. 20-21 working on edge ruts, moving operation.

Monroe County
Construction
:
Route 15- Job 45% complete, crews will be working in Audrain County at Mexico, work postponed in Monroe County area this week; when crews are working one lane road with possible width restrictions of 10 ft.; location 24.3 miles in Audrain and Monroe Counties from one mile north of Route 22 to just north of Route 54 at Mexico.
Route 151 - (Includes Shelby County) - Scheduled to begin Oct. 19 - Resurfacing from Business Route 36 at Clarence to Route 24 at Madison, 22 miles.
Maintenance:
All routes - Oct. 13-23 mowing, moving operation with blocker truck.
Route 15 - Oct. 19-23 hot mix patching, single lane traffic with flaggers.

Montgomery County
Construction
:
Route AC - Project 58% complete - Welding deck clips, install metal decking forms, and pour back walls, set overhang brackets. Sept. 8 thru Nov. 20 road closed to rehabilitate Cuivre River Bridge; detours over Routes AC, K, W, BB, 161.
Maintenance:
Minor routes - Oct. 13-16 mowing, moving operation with blocker truck.
Route MM - Oct. 14-16 fly coating roadway, one lane traffic with flaggers.
I-70 median & shoulders - Oct. 19-23 mowing operation.

Pike County
Construction
:
Route 61 - 22% complete, shoulder work in progress. Diamond grinding in southbound lanes with one lane closed during daytime work hours; three disconnected pieces in both north and southbound lanes between Bowling Green and Eolia.
Maintenance:
Various routes - Oct. 13-23 mowing, moving operation with blocker truck.
Route 79 (at Claire Creek) - Oct. 21-23 cleaning box culvert, signs & flaggers as necessary.
Route 79 (repair is on N. 7th Street in Louisiana) - Oct. 13 & 14 concrete replacement, one lane traffic with flaggers and could remain one lane until approximately 7-8 p.m. to allow adequate drying time for the concrete.  Minor delays should be expected.
Route HH - Oct. 21-23 hot mix spot patching, one lane traffic with flaggers.

Ralls County
Construction
:
Route P - Job 58% complete; Painting beams flanges, weld deck clips, install metal decking forms and substructure repair. Sept. 22 thru Nov. 20 road closed to rehabilitate Spencer Creek Bridge; road will be closed at the bridge with detours over Routes K, 19, 154.
Maintenance:
Supplementary Routes - Oct. 13-16 mowing, moving operation with follow truck.
Routes 61 and 36 - Oct. 13-16 working on erosion control under bridges, one lane with signs.
Supplementary Routes - Oct. 19-23 mowing, moving operation with follow truck.
Routes 61 and 36 - Oct. 19-23 working on erosion control under bridges, one lane with signs.

Scotland County
Maintenance
:
Various Routes - Oct. 19-23 painting H-piles under bridges, no lane closures.
Routes H, Z, N, EE, C, CC, DD, B and JJ - Oct. 13-16 mowing, moving operation with follow truck.
Routes T, A and C - Oct. 13-16 patching potholes on bridges, moving operation.
Routes D, T, W, M, MM, A, Z, U and E - Oct. 19-23 mowing, moving operation with follow truck.
Routes P, AA, NN, A, W, D, 81S, Y, HH and BB - Oct. 19-23 mowing, moving operation with follow truck.

Shelby County
Construction
:
Route 151 - (Includes Monroe County) - Scheduled to begin Monday, Oct. 19 - Resurfacing from Business Route 36 at Clarence to Route 24 at Madison, 22 miles.

Route 36 - Project Status: Project 75% complete - Shelby County area - Contractor will be laying base rock on mainline from Route T to Shelbina and Erosion Control - Seeding acreage near Shelbina K. The north Ramps at Route 36/15 at Shelbina and Co. Rd. 490 remain closed. The westbound on/off ramps at Routes 36/15 at Shelbina are closed off; the contractor will pave a portion of the new highway, rebuild part of the ramps, and then tie it in to the existing highway. Motorists driving west will be directed to take the first Shelbina exit to access Route 15 north and south. Detours clearly signed. Marion County area - Contractor will be paving from just west of Monroe City to the Marion/Shelby County Line. Grading just west of Monroe City on the eastbound lanes. Motorist should take caution for trucks slowing & turning on & off the highway. This will be a work zone and the speed limit will be 45 mph. Traffic traveling on the 3 miles of new westbound lanes approximately 1 ½ miles west of Monroe City, or just west of the Route Z interchange. Motorists wishing to enter and exit Monroe City using Business Route 36 on the west end of town will be using a new temporary gravel crossover in the median area on Route 36.
Maintenance:
Routes 151, MM, DD, TT, A, WW, CC, PP, V, Z, T, AA, U, HH, FF and KK - Oct. 13-16 mowing, moving operation with follow truck.
Routes K, H, N, P, E and M - Oct. 13-16 mowing, moving operation with follow truck.
Route 15 - Oct. 19 ditch work, temporary lane closure.
Routes W J - Oct. 20-23 working on edge ruts repair, moving operation.
Routes 36,15 and 151 - Oct. 19-23 blading shoulders and patching potholes, both lanes open.

Warren County
Construction
:
Interstate 70 westbound - Project 25% complete; Weather permitting, Oct. 12 - 16 contractor will resurface westbound from m.m.186 to 193. Due to concerns with safety of traveling public and workers, the ramps at Route A & B, and the ramp from Route 47 to west bound I-70, will be closed for short periods of time, approximately 3 to 4 hours, within the next two weeks, sometime between the hours of 6:00 PM and 7:00 AM. It is expected that only one ramp will be closed at any given time, and changeable message boards will be in place advising motorists to use outer roads for access to/from I-70 during the ramp closures. Work will take place at night, from 6:00 p.m. to 7:00 a.m. Resurfacing from just west of Route 47 to the Montgomery county line.
Maintenance:
Minor routes - Oct. 13-16 mowing, moving operation with blocker truck.
I-70 median & shoulders - Oct. 19-23 mowing operation.

   
   