Counties Impacted
Lincoln
Route Impacted
47
61
Work Type
Interchange Improvements
In Progress

Project Summary

This interchange improvement project will replace the existing Missouri Route 47 bridge over U.S. Route 61 and modify the interchange to a diverging diamond design that will navigate traffic volumes more efficiently. Over the course of the project, major improvements on Missouri 47 will include:

  • Widening the bridge deck over U.S. 61
  • Corridor improvements from Turnbull Trail to East Cherry Street/Wilson Road, including two dedicated lanes in each direction
  • An ADA-compliant pedestrian walkway
  • Relocation of the Frenchman Bluff Road intersection

Project Milestones

Complete
Conceptual design public meeting

May 2019

milestone_icon
Complete
Work on preliminary design

2019 / 2020

milestone_icon
Complete
Present design at public meeting

November 2022

milestone_icon
Complete
Project Awarded

June 2024

Contractor: KCI Construction Company
Contract Amt: $15.4M

milestone_icon
In Progress
Construction
milestone_icon
Project Completion

Fall 2025

milestone_icon

News Releases

Frequently Asked Questions

How much does the project cost? 

Approximately $15.4 million

What is the construction schedule for the project?

Stage 1 - Summer 2024 through Fall 2024

  • Install new and temporary pavement around the interchange to widen the bridge and MO 47 and relocate the entrance for the businesses in the southeast quadrant.

Stage 2 - Fall 2024 through Winter 2024

  • Construct the northern half of the interchange as well as relocate the Frenchman Bluff entrance.

Stage 3 - Early 2025 through Summer 2025

  • Construct the southern half of the interchange as well as relocate the Frenchman Bluff entrance.

Stage 4 - Summer 2025 through Fall 2025

  • Install concrete islands and barrier, permanent signals and lighting around the interchange.

What are the anticipated impacts? 

During the bridge closures, a signed detour will divert traffic on the following routes:

  • MO 47 (Eastbound/Westbound) will use a signed detour over East Cherry Street to South Lincoln Drive then northbound to MO 47 or southbound to the South Lincoln Drive interchange. Travelers wishing to access U.S. 61 from MO 47 will utilize this detour.
  • U.S. 61 (Northbound) to MO 47 (Westbound toward Hawk Point) will utilize the South Lincoln Drive interchange to reach MO 47
  • U.S. 61 (Northbound/Southbound) traffic will be diverted up and over the existing interchange ramps
  • The U.S. 61 (Northbound) on-ramp at Old Cap Au Gris Road will be closed to traffic

During the Right Turn Only Restrictions during Stage 2-3, a signed detour will divert traffic on the following routes:

  • MO 47 (Eastbound/Westbound) will use a signed detour over East Cherry Street to South Lincoln Drive then northbound to MO 47 or southbound to the South Lincoln Drive interchange. Travelers wishing to access U.S. 61 from MO 47 will utilize this detour.
  • U.S. 61 (Northbound) to MO 47 (Westbound toward Hawk Point) will utilize the South Lincoln Drive interchange to reach MO 47
  • U.S. 61 will have late night road closures while crews set bridge beams in place. These closures will be short-term lasting up to 20 minutes and occur between midnight and 4 a.m.

How can I stay updated about the project? 

Stay updated on news about roadwork in your area by signing up for emails at eUpdates at MoDOT.org

Who can I contact if I have further questions? 

Questions about the project may be directed to Jeff Niemeyer, Area Engineer, at jeffrey.niemeyer@modot.mo.gov

Project Contacts