Counties Impacted
Butler
Route Impacted
67
Work Type
Corridor Upgrades
In Progress

news Project Update

The Future I-57 project in Butler County will include upgrading U.S. Route 67 to interstate standards from the Route 160/158 interchange south of Poplar Bluff, Missouri to the MO/AR State line. This will primarily be accomplished by constructing four new lanes west of the existing U.S. 67 pavement and converting the existing pavement into an east outer road.

The entire project limits are broken down into five phases: Phases 1A and 1B, as well as Phases 2-4.

Phase 1A has been completed.

Phases 1B and 2 are under construction and include upgrading U.S. 67 to four lanes from near the Route 160/158 interchange to County Road 352. An online form is available below or at modot.org/form/67trafficshift for anyone interested in receiving an alert about the upcoming traffic shift. 

Phase 3 includes upgrading U.S. 67 to four lanes from County Road 352 to near County Road 272. Within this nearly five-mile section, an interchange at Neelyville, an overpass at County Road 350/Route MM, and an underpass at County Road 270 connecting to existing U.S. 67 will be constructed.

Phase 4 includes upgrading the remaining three-mile section of U.S. 67 north of the Arkansas State line to four lanes and constructing an interchange at State Line Road. Phase 4 will be funded by general revenue provided by the state legislature and Governors Parson and Kehoe.

In order to upgrade U.S. 67 to interstate standards, at-grade crossings along this section of the corridor must be permanently closed.

Project Milestones

Complete
Virtual Public Hearing: Phases 1A & 1B

August 3, 2021

milestone_icon
Complete
Virtual Public Hearing: Phase 2

Feb. 3, 2022

milestone_icon
Complete
Public Meeting: Phase 3

Oct. 19, 2022

milestone_icon
Complete
Construction Begins for Phase 1A
Route 160/158 Interchange

Summer 2022

milestone_icon
Complete
Completion of Phase 1A
Route 160/158 Interchange

Nov. 2023

milestone_icon
Complete
Public Hearing for Phases 3 & 4

Sept. 10, 2024 from 4-7 p.m. at Neelyville Schools 

More Details

milestone_icon
Complete
Phases 1B and 2 Awarded
Oct. 2, 2024
milestone_icon
Construction of Phases 1B and 2

Anticipated Completion Fall 2026

milestone_icon
Anticipated Award of Phase 4
three-mile section of U.S. 67 north of the MO/AR State line

Fall 2026

milestone_icon

road MoDOT Preps for Traffic Shift on U.S. 67 in Butler County, Asks for Local Motorists’ Assistance

MoDOT is preparing for new traffic patterns along U.S. Route 67 between U.S. 160 and Route MM in Butler County in the coming weeks.

During the transition, construction crews will shift traffic from the existing U.S. 67 roadway to the newly constructed four-lane facility. To minimize the duration of impacts, construction crews will work continuously to complete the transition within an anticipated 36-hour period.

“Tentatively, MoDOT anticipates the transition to occur in mid-September. While the transition is expected to take approximately 36 hours, we do understand the impacts to traffic, though brief, will be significant during that time,” said MoDOT Resident Engineer Matt Wilkerson.

Wilkerson explained while an exact date has not been set, that’s where MoDOT would like the public’s assistance.

“We are asking residents and local travelers who live or travel along the section of U.S. 67 between U.S. 160 and Route MM to help us stay in contact as we set an exact date for the transition,” he said. “Individuals are encouraged to provide their contact information to MoDOT through the online form on the project webpage to receive an alert from us once that date is established.”

An online form is available below or at modot.org/form/67trafficshift for anyone interested in receiving this information via physical mail and email (if available).

Motorists can expect to see the following work during the continuous, 36-hour operation:

1. Southbound traffic will be transitioned onto the newly constructed southbound lanes just south of the U.S. 160 intersection and then return back to existing U.S. 67 by use of a crossover located between County Road 352 and Route MM.

2. Once southbound traffic is transitioned to the new lanes, EXISTING U.S. 67 within the same limits will be converted to one lane, no passing for NORTHBOUND travel ONLY!

3. Once the pavement connection from the newly constructed northbound lanes to existing U.S. 67 is complete, then northbound traffic will transition to the new northbound lanes.

4. Once northbound traffic is on the new lanes, existing U.S. 67 from County Road 352 to the end of Hawkeye Lane will then become the East Outer Road. For a short time, the East Outer Road will be closed between the southern end of Hawkeye Lane until construction crews complete a temporary connection of the East Outer Road. The East Outer Road will return to bidirectional traffic conditions except for a small section to be controlled by temporary signals while crews complete the permanent connection of the East Outer Road.

Once this initial traffic transition is complete, northbound and southbound U.S. 67 traffic will remain in a one lane roadway condition along the northern limits of the project as construction crews complete the four-lane connection.

Webform

PROVIDE CONTACT INFORMATION: U.S. 67 in Butler County from U.S. 160 to Route MM

Residents & Local Travelers

The Missouri Department of Transportation is preparing for new traffic patterns along U.S. Route 67 between U.S. 160 and Route MM in Butler County in the coming weeks. 

During the transition, construction crews will shift traffic from the existing U.S. 67 roadway to the newly constructed four-lane facility. To minimize the duration of impacts, construction crews will work continuously to complete the transition within an anticipated 36-hour period. 

While an exact date has not yet been set, MoDOT is asking residents and local travelers who live or travel along this section of U.S. 67 to help MoDOT communicate important information about the upcoming traffic shift. 

Individuals are encouraged to provide their contact information through the form below to receive an alert from us once that date is established.

Your Name

Mailing Address

Please enter your mailing address for an additional alert regarding the traffic shift. 

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.
Image
View the Aerial for Future I-57 in Butler County

Overview of Phases

Click below to view an overview of the proposed project to upgrade U.S. Route 67 in Butler County to four lanes in preparation for Future I-57. The entire project limits are broken down into five phases: Phases 1A and 1B, as well as Phases 2-4. Phase 1A has been completed. Phases 1B and 2 are under construction.

View Overview
Image
Environmental Impact Statement Feature Block

NEPA Reevaluation of EIS

Please click the link below to review the NEPA Reevaluation of the U.S. Route 67 Environmental Impact Statement. During the reevaluation, MoDOT and the City of Poplar Bluff reviewed the 2005 EIS as it pertains to the 10-mile section of U.S. 67 from the Route 160 interchange to two miles north of the state line near County Road 274.

Learn More
Image
Email Updates_feature block

Stay Up-to-Date

Stay up-to-date on the next steps for the Future I-57 project by signing up to receive email updates! To subscribe, click the link below and select the option for "Future I-57 Project" under the Southeast District's Routes & Projects. We will keep you in the loop as new information is released!

Sign-Up

project Public Meeting Information Archive

Phase 1A and 1B

Virtual Public Hearing: Aug. 3, 2021

Phase 2

Virtual Public Hearing: Feb. 3, 2022

Phase 3

Public Meeting: Oct. 19, 2022

Phases 3 and 4

Public Hearing: Sept. 10, 2024

Image
ARDOT logo

Future I-57 in Arkansas

The Arkansas Department of Transportation (ARDOT) and Federal Highway Administration (FHWA) conducted three location public hearings to present and discuss the Draft Environmental Impact Statement (DEIS) for the proposed Walnut Ridge to Missouri State Line (Future I-57) connection in Clay, Greene, Lawrence, and Randolph counties.

Learn More

project For More Information

Contact Photo
Tim Pickett_District Design Engineer
Tim Pickett
Title
District Design Engineer
Department
Southeast District
Contact Info

(573) 472-9003

Contact Photo
Katy Bower_Area Engineer_Southeast District
Katy Bower
Title
Area Engineer
Department
Southeast District
Contact Info

(573) 380-0744