888 - Ask MoDOT (275-6636)
The Missouri Department of Transportation plans to improve four bridges on Route 114 in Stoddard County. The upcoming bridge projects are grouped into two lettings in January 2025 and December 2026, tentatively.
Improvements to the Route 114 bridges to be let in Jan. 2025, include:
Construction of the bridges over Drainage Ditch 5 and Little River Drainage Ditch could begin as early as spring 2025. During this time, the roadway will be closed in the vicinity of each bridge for approximately 120 days.
Improvements to the Route 114 bridges to be let in Dec. 2026, include:
Construction of the two bridges in the Dec. 2026 letting could begin as early as spring 2027. Work on both bridges will begin simultaneously. The closure at Dexter Creek will be in place for approximately 70 days. The closure at the Union Pacific Railroad will be in place for approximately 120 days.
View Location Maps > Please share your thoughts by submitting the form below. Your comments will be sent directly to the project team.