Callaway County Route D/I-70 Bridge Roadway and Bridge Improvements

The Callaway County Route D bridge over I-70, approximately 2.3 miles southwest of Williamsburg, was replaced. 

The contract was awarded to Emery Sapp and Sons, which submitted the low bid of $1,575,022. 

This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

 

Project Details

When: 

June-December, 2020. 

Cost:

$1,575,022

Work Taking Place:

Crews replaced the Route D bridge over I-70 and made roadway improvements at various locations along the north outer road of I-70 near the D bridge.

Project Milestones

Complete
Project Awarded
November 2019

The Missouri Highways and Transportation Commission approved a contract to Emery Sapp and Sons, which submitted the low bid of $1,575,022. 

milestone_icon
Complete
North Outer Road of I-70 (Old Route 40) Road Work Begins
June 2020
milestone_icon
Complete
One Night I-70 Closure for Construction
June 23, 2020
milestone_icon
Complete
Route D Bridge Closure for Construction
June 23, 2020

 

 

 

milestone_icon
Complete
Completion of Project
October 2020
milestone_icon