Enon Creek Bridge Replacement

Below are details, resources and news about the replacement of the Moniteau County Route A bridge over Enon Creek, located west of Enon.  This bridge has reached a condition where replacement is necessary. 

Project Details

When:

The project took place in 2022.

Cost: 

The contracted cost of the project was $1,965,191 (includes the Route A Bridge in Cole County).

Work Taking Place: 

The replacement of the bridge.  The new bridge raises the roadway grade by six inches to help with flooding. 

Project Milestones

Complete
Public Comment Period
June 1 - 15, 2021
milestone_icon
Complete
Bid Awarded
March 1, 2022

The Missouri Highways and Transportation Commission awarded the contract to Gene Haile Excavating, which submitted the low bid of $1,956,191. The contract also includes the Cole County Route A bridge replacement over South Moreau Creek.

milestone_icon
Complete
Construction of New Bridge
Began October 21, 2022
milestone_icon
Project Completion

The new bridge was reopened to traffic on December 9, 2022. 



 

milestone_icon